HomeOil and GasOman Gas Pipeline Expansion Plans Move Forward

Oman Gas Pipeline Expansion Plans Move Forward

Oman gas pipeline expansion plans move forward as OQ Gas Networks (OQGN) outlines a bold strategy to grow the national gas grid. The company seeks to increase both the pipeline length and the total gas transport capacity to meet rising demand.

OQGN currently operates Oman’s entire gas transportation network. It plans a 5.6 percent increase in network length. Additionally, it aims to raise capacity by 13.1 percent. These efforts support Oman Vision 2040 and reflect the goals of energy diversification and infrastructure development.

Today, the gas pipeline system spans over 4,235 kilometers. However, Oman gas pipeline expansion plans will stretch it to nearly 4,500 kilometers. The company also plans to grow capacity from 70.48 billion cubic meters to about 80 billion cubic meters.

Moreover, gas demand is forecast to rise by 4.7 percent per year. In the past year, OQGN delivered 42.98 billion cubic meters. That marked a 3.5 percent increase from the year before. Oman gas pipeline expansion efforts will help meet this growing need from key sectors.

Petroleum Development Oman (PDO) provided 56.8 percent of the total gas supply. The gas was delivered through the Integrated Gas Company (IGC), Oman’s Unified Shipper. Meanwhile, the largest consumer remained the LNG sector, which used 41.3 percent. The industrial and commercial sectors followed with 27.6 percent of total demand.

Oman gas pipeline expansion includes ten active infrastructure projects. One of the most important is the Fahud-Suhar Loop Line. This project adds a 193-kilometer pipeline to an existing route and includes a 2-kilometer spur line. Once completed, it will increase Suhar’s pipeline capacity by more than 26 percent.

Another initiative is the Central Rich and Lean Gas Segregation Project. This involves a blending station and a 65-kilometer loop line. It improves the gas value by separating rich and lean gas. The total investment in this Oman gas pipeline expansion project exceeds 70 million riyals.

Furthermore, OQGN continues developing a Long-Term Network Development Plan (LTNDP). This tool forecasts future gas needs over seven years. It helps government bodies and regulators plan infrastructure and balance supply and demand.

In conclusion, Oman’s gas network growth ensures future energy security and supports the country’s expanding industrial sector. Through careful planning and major investments, Oman is getting ready to handle increasing demand across all regions.